AI data center dossier

EDF / OpCore Montereau AI Data Center

Montereau-Vallee-de-la-Seine, Ile-de-France, France/datacenters/edf-opcore-montereau-ai-data-center-france.html

Country

France

Operator

OpCore, EDF, iliad Group, InfraVia Capital Partners

Energy

French low-carbon grid

Tracked capacity

700 MW

Grid-connection envelope | Trade corroborated

700 MW is the reported authorized grid-connection envelope for the Montereau site, not confirmed IT load.

Evidence profile

Readiness reflects whether the record has citations, narrative context, structured power data, coordinates, and at least one dated milestone.

Readiness

86%

Sources attachedVerified

2 citations linked

CoordinatesMissing

No map point published yet

Capacity scopeScoped

Grid-connection envelope | Trade corroborated

Timeline evidencePartial

2 dated fields available

Machine-readable outputsPublished

HTML, JSON, and GeoJSON all available

Record Notes

EDF and OpCore entered exclusive negotiations for a high-power data center at the former Montereau-Vallee-de-la-Seine thermal power plant southeast of Paris. Data Center Dynamics reports the project as a possible EUR 4 billion hyperscale data center on a 20-hectare EDF site, with several-hundred-MW data center capacity and an authorized grid connection of up to 700 MW. ADCI splits this path out of the AION record because the EDF/OpCore Montereau project is a distinct site and is not verified as the selected AION AI Gigafactory location. The selected 700 MW value is treated as an authorized grid-connection upper envelope, not confirmed IT load. No map point is selected until source-backed parcel coordinates are added.

Analyst Flags

No obvious coverage gaps detected in the current structured record.

Timeline Signals

Announcement2025
Earliest market signal2025

Related Facilities

Frequently asked questions

How big is EDF / OpCore Montereau AI Data Center?
EDF / OpCore Montereau AI Data Center has 700 MW of tracked capacity (Grid-connection envelope | Trade corroborated), located in Montereau-Vallee-de-la-Seine, Ile-de-France, France. It ranks #32 globally by selected capacity among 294 tracked records.
What is the status of EDF / OpCore Montereau AI Data Center?
EDF / OpCore Montereau AI Data Center is currently planned. Known timeline milestones: Announcement 2025, Earliest market signal 2025.
Who operates EDF / OpCore Montereau AI Data Center?
EDF / OpCore Montereau AI Data Center is operated by OpCore and EDF and iliad Group and InfraVia Capital Partners. Structured intelligence reports are available for OpCore Operator Report and EDF Operator Report and iliad Group Operator Report and InfraVia Capital Partners Operator Report and France Country Report.
What energy source does EDF / OpCore Montereau AI Data Center use?
EDF / OpCore Montereau AI Data Center is powered by french low-carbon grid energy and is focused on mixed workloads. This is backed by 2 cited sources.